Türkiye

ENERGO-PRO entered the Turkish market in 2006 as part of its further expansion abroad. Four years later, the company acquired a portfolio of 5 partially built hydropower plants. The company aims to consolidate its position in the Turkish energy market where it belongs to medium-sized hydropower operators in the hydropower sector. ENERGO-PRO now owns and operates 6 hydropower plants in Türkiye with a total installed capacity of 373.4 MW and an average annual output of 990 GWh.

In 2020, Alpaslan 2 hydropower plant successfully passed the necessary tests and obtained a permit to start operation. The new Alpaslan 2 hydropower dam is located on the Murat River in Türkiye. The plant has 4 Francis turbines with a total installed capacity of 280 MW. It is the largest Czech investment in the hydropower sector since November 1989.

Market entry

2006

Assets

6 hydropower plants

Number of employees

145

Installed capacity

373.4 MW

Annual generation

990 GWh

Hamzalı HPP

History

The HPP was put into operation in November 2008, and it has been part of ENERGO-PRO since 2010. It uses the water resources of the Kizilirmak River. The HPP is fitted with two Kaplan turbines.

Type of power plant

Run-of-the-river

Installed capacity

16.7 MW

Annual electricity production

51 GWh

Reşadiye I Cascade

History

The HPP was put into operation in 2009, and it has been part of ENERGO-PRO since 2010. It is part of a three-stage cascade on the Kelkit River. The HPP is fitted with two Francis turbines.

Type of power plant

Run-of-the-river

Installed capacity

15.7 MW

Annual electricity production

99 GWh

Reşadiye II Cascade

History

The HPP was put into operation in 2009, and it has been part of ENERGO-PRO since 2010. It is part of a three-stage cascade on the Kelkit River. The HPP is fitted with two Francis turbines.

Type of power plant

Run-of-the-river

Installed capacity

26.1 MW

Annual electricity production

164 GWh

Reşadiye III Cascade

History

The HPP was put into operation in 2009, and it has been part of ENERGO-PRO since 2010. It is part of a three-stage cascade on the Kelkit River. The HPP is fitted with two Francis turbines.

Type of power plant

Run-of-the-river

Installed capacity

22.5 MW

Annual electricity production

134 GWh

Aralık HPP

History

The HPP was put into operation in April 2010, and it has been part of ENERGO-PRO since 2010. It is located in Aralık Bay in the Black Sea Region of Turkey – upstream of the Muratli Dam. The HPP is fitted with two Pelton turbines.

Type of power plant

Run-of-the-river

Installed capacity

12.4 MW

Annual electricity production

55 GWh

Alpaslan 2 HPP & dam

History

ENERGO-PRO acquired the project of Alpaslan 2 HPP in 2017. The HPP was put into operation in 2020 after the installation of the first Francis turbine. The construction was then successfully completed in 2021, and all 4 Francis turbines are now in operation. The installed capacity of the plant is 280 MW. Alpaslan 2 has thus become the largest hydropower plant in the ENERGO-PRO's portfolio and the largest Czech investment in hydropower since 1989.

The plant is equipped with two 110 MW turbines and two 30 MW turbines. From the perspective of optimising the power generation, this is an ideal layout which makes full use of the dam's potential and of minimum environmental flow. The runners of the large turbines have a diameter of 3,800 mm, those of the small turbines have the diameter of 1,960 mm. A technical highlight is that the large runners were manufactured as one large casting – a monoblock – and subsequently machined. This makes them the largest Francis turbine runners in Turkey made by this method.

Type of power plant

Hydropower plant with reservoir

Installed capacity

280 MW

Annual electricity production

700 GWh

Company

ENERGO-PRO Türkiye Holding A.Ş.


Address